Used in the context of production plans for the calculation of material requirements, then for the generation of production movements (launches).
In the latter they play a key role in connection with external tasking programs, such as Microsoft Project®, for which we can provide integration parts and customizations dedicated to the needs.
For each calendar you can define working days, non-working days and holidays. The program provides a predefined calendar called “Standard”.
Simply select the year, month, day in the left grid, then the corresponding option in the “Select Dates” frame: Work Day, Non-Working Day.
With regard to the “Work Day” it is finally necessary to define the daily working time: From … to … (AM/PM).
It is possible to use the “Saturday and Sunday” button to re-enter the weekly weekdays. This functionality should be used if a standard value reset is needed or because a new production calendar has been created, to which the standard needs to be defined.